L-T has emerged as lowest bidder for constructing three buildings under Central Vista projectInfrastructure firm Larsen - Toubro (L-T)
Limited on Monday emerged as the lowest bidder for the construction and maintenance of the first three buildings of the Common Central
Secretariat under the Central Vista redevelopment project.According to the Central Public Works Department's (CPWD) bid documents,
L-T Limited quoted around Rs 3,141 crore, which is 3.47 per cent less than the estimated cost
The firm submitted a total bid amount of Rs 31,41,99,87,657.NCC Ltd quoted the second lowest bid amount of around Rs 3,318 crore for the
project, which was 1.94 per cent more than the estimated cost.The bid documents show that Tata Projects Limited quoted around Rs 3,546
crore, which is 8.96 per cent more than the estimated cost.These new buildings will come up on the plot where the Indira Gandhi National
Centre for the Arts is located.An official said that the the Board of Central Public Works Department (CPWD), which has been executing the
Modi government's ambitious Central Vista Redevelopment Project, will decide on the tender work award in the next few days.The official
added that usually, the lowest bidder (L-1) is awarded the contract.Four infrastructure firms, Tata Projects, Uttar Pradesh Rajkiya Nirman
Nigam Limited, Larsen - Toubro Limited and NCC Limited had submitted technical bids for the construction of the three buildings of the
Common Central Secretariat.Last month, the CPWD had revised the estimated cost of construction and maintenance of the three buildings of the
Common Central Secretariat.The estimated cost of construction and maintenance of these three buildings had been revised to around Rs 3,254
crore from Rs 3,408 crore.Tata Projects Limited is constructing a new parliament building while Shapoorji Pallonji and Company Limited is
executing the redevelopment work of the Central Vista Avenue stretching from Rashtrapati Bhavan to India Gate.